PROJECT EXPERIENCE / TECHNICAL LIBRARY

Real roofs. Real constraints. Documented decisions.

These case studies focus on the technical reasoning behind the work: what was retained, what had to be repaired, how the build-up was coordinated and which details controlled the final result.

4 documented projects2 refurbishment technologies1 system-led approach
ALL PROJECTSLIQUID SYSTEMSBITUMINOUS SYSTEMSROOF REFURBISHMENT
LIQUID ROOF REFURBISHMENT01

Ageing asbestos-cement roof: repair before replacement.

A repair-led strategy combining targeted void filling, flexible joint treatment, reinforced detailing, primer and a continuous liquid-applied protective finish.

Existing roof retainedTargeted detail repairWinkler liquid system
VIEW CASE STUDY →
BITUMINOUS ROOF REFURBISHMENT02

Old torch-on roof: rebuild what matters beneath the membrane.

Approximately 2,500 m² of roof refurbishment with selective deck replacement, corrected falls, new outlets and a two-layer Börner SBS system.

≈2,500 m²Deck + drainage repairTwo-layer SBS system
VIEW CASE STUDY →
WARM ROOF + TERRACES03

One torch-safe system across apartment roofs and terraces.

A complete 630 m² warm-roof build-up connecting self-adhesive vapour control, PIR insulation, underlay, cap sheet and corner drainage details.

≈630 m²Roofs + terracesBörner torch-safe hybrid
VIEW CASE STUDY →
LIQUID ROOF REFURBISHMENT04

Two apartment blocks: H₂O refurbishment with safe access.

A 1,430 m² liquid refurbishment over existing torch-on membranes, coordinated with through-roof outlets and a permanent cable lifeline.

1,430 m² totalTwo apartment blocksWinkler H₂O
VIEW CASE STUDY →
THE CASE-STUDY METHOD

The membrane is documented as part of the decision—not as the whole story.

Each project connects roof condition, substrate work, drainage, system selection and critical interfaces. Product names remain useful, but only inside the complete technical context.