CASE STUDY / 02 · BITUMINOUS ROOF REFURBISHMENT

Restoring an ageing 2,500 m² torch-on roof.

The project went beyond laying new membrane. Damaged deck areas were replaced, drainage was improved and vulnerable roof details were rebuilt before the two-layer Börner system was completed.

AREAApproximately 2,500 m²
EXISTING ROOFAgeing torch-on membrane system
REPAIR SCOPEDeck, falls, outlets and ventilation
WATERPROOFINGTwo-layer Börner SBS system

This was a large refurbishment of an existing torch-on roof covering approximately 2,500 m². The aim was to retain serviceable parts of the roof while rebuilding the areas that could compromise the new waterproofing system.

The roof needed more than an overlay.

Parts of the plywood and OSB deck had deteriorated and required selective replacement. Existing outlets were renewed, additional ventilation shafts were introduced and local falls were reshaped so that water moved toward the drainage points instead of remaining on the field area.

Those works were completed before the main two-layer membrane build-up. This kept the waterproofing sequence tied to the real condition and geometry of the roof rather than treating the old surface as a uniform substrate.

01

Repair

Open the failed areas and replace damaged plywood or OSB instead of bridging over them.

02

Drain

Replace outlets and correct local falls so water has a clear route off the roof.

03

Protect

Complete the prepared roof with a compatible primer, underlay and cap sheet.

The complete Börner waterproofing route.

The field build-up used GEBÖRTOL V Rapid primer, MONOPLEX SBS PV 180 S4 underlay and POLY-ELAST PV 180 S4 cap sheet. TEK Bitumen Wedges were used at selected uninsulated changes of direction so the membranes were not forced through a sharp internal corner.

01Surface preparation

GEBÖRTOL V RAPID

GEBÖRTOL V Rapid was applied to compatible prepared areas as the bituminous adhesion primer beneath the first waterproofing layer.

OPEN MATERIAL →
02Torch-applied underlay

MONOPLEX SBS PV 180 S4

The reinforced SBS underlay formed the first waterproofing layer across the prepared roof and repaired substrate.

OPEN MATERIAL →
03Mineral cap sheet

POLY-ELAST PV 180 S4

The reinforced SBS cap sheet completed the two-layer system and provided the exposed weathering surface.

OPEN MATERIAL →
04Uninsulated angle details

TEK BITUMEN WEDGE

Bituminous angle fillets supported selected deck-to-upstand changes of direction where the roof detail did not include insulation.

OPEN MATERIAL →
TECHNICAL PRINCIPLE

A new cap sheet cannot correct a weak deck or reverse a poor fall. Substrate repairs and drainage improvements were part of the waterproofing work, not separate cosmetic extras.

How the refurbishment was sequenced.

  1. 01
    Survey and repair mapping

    The existing torch-on surface, deck condition, drainage points and vulnerable details were reviewed before the refurbishment zones were defined.

  2. 02
    Selective deck replacement

    Failed plywood and OSB sections were opened up and replaced to provide a sound base beneath the retained and renewed roof areas.

  3. 03
    Drainage and falls correction

    Outlets were replaced and local roof falls were reformed to improve the flow of water toward the drainage points.

  4. 04
    Ventilation and angle detailing

    Additional ventilation shafts were incorporated and weathered into the system. Selected uninsulated upstand junctions received bituminous angle fillets before the membranes were dressed through the change in direction.

  5. 05
    GEBÖRTOL V Rapid + MONOPLEX SBS PV 180 S4

    Compatible prepared surfaces received the bituminous primer before the reinforced SBS underlay was installed as the first waterproofing layer.

  6. 06
    POLY-ELAST PV 180 S4

    The mineral-finished cap sheet completed the two-layer waterproofing system across the field, laps, outlets, penetrations and perimeter details.

The completed roof.

The project delivered a renewed two-layer waterproofing surface across approximately 2,500 m² while addressing the defects beneath it. The repaired deck provided a sound base, the reworked falls improved drainage and the replacement outlets and added ventilation shafts were integrated into the new membrane system.

The successful part of this refurbishment was not simply the new cap sheet.
It was correcting the deck, drainage and details before the roof was closed again.
PROJECT RECORD / SYSTEM STATUS

A completed project is not a current specification.

This case study records the work and product route used on this particular roof. Current Börner product availability, certificates, fire classification and the exact project build-up must be checked before the system is considered for new work.